Outcome
The pipeline was successfully constructed in a single year and on programme. During construction, Bell Ingram worked closely with Shell and their contractors, providing 10 land liaison officers, five drainage consultants and over 15 agricultural inspectors, along with five land agents along the route. On completion of the pipeline construction, we negotiated compensation claims for crop losses and disturbance and we have continued to provide crop loss claim and drainage services during the operational phase. Bell Ingram also provide a development monitoring service through our Planning Consultant, working closely with the pipeline operator.